Concrete · Intermediate
How to Pour a Concrete Slab
Formwork, base prep, mixing and finishing — a complete beginner-friendly walkthrough.
- • Shovel
- • Wheelbarrow
- • Screed board
- • Bull float
- • Edger
- • Groover
- • Rubber gloves
- • Safety glasses
- • Ready-mix concrete or 60/80 lb bags
- • 2x4 lumber for forms
- • Rebar or wire mesh
- • Compactable gravel base
- • Vapor barrier (interior slabs)
- • Concrete sealer
Step-by-step
- 1
Plan and mark the slab
Lay out the perimeter with stakes and mason line. Confirm dimensions square by measuring diagonals — they must match within 1/8". Slope 1/4" per foot away from any structure for drainage.
- 2
Excavate and compact the base
Dig 6–8" deep. Add 4" of compactable gravel in 2" lifts, tamping each lift. A firm base is what keeps a slab from cracking; skip this and the concrete will telegraph every soft spot.
- 3
Build forms
Screw 2x4s to stakes every 3–4 feet along the perimeter. Check the top of forms with a level — that's the finish grade of your slab. Coat form faces with form-release oil or old motor oil for clean removal.
- 4
Set reinforcement
Lay 6x6 W1.4 wire mesh or #3 rebar in a 16" grid, elevated on 2" chairs so it sits in the middle of the slab thickness. Reinforcement in the bottom does nothing.
- 5
Pour and screed
Start pouring at the far corner. Rake concrete into place slightly proud of the forms, then screed with a 2x4 in a sawing motion across the forms. Work in 8–10 ft sections.
- 6
Bull float, edge, and groove
Once bleed water disappears, bull float to close the surface. Run an edger along the perimeter and cut control joints every 8–10 feet with a groover to control cracking.
- 7
Final finish and cure
For a broom finish, drag a soft broom across after the surface firms up. Cover with plastic sheeting and keep damp for 5–7 days. Do not walk on the slab for 24 hours; do not park on it for 7 days.
Related calculators
Was this guide helpful?
People also searched
Safety note: this guide is educational. Always follow local building codes, pull required permits, and hire a licensed pro for structural, electrical, gas or plumbing work when in doubt.
More guides
How to Install a Pre-Hung Interior Door
Shimming, plumbing and hanging a pre-hung door so it latches cleanly and stays where you leave it.
Read FramingHow to Frame a Basement Wall
Moisture control, wall placement, bottom plates on concrete and the framing sequence for a basement finish that lasts.
Read PlumbingHow to Replace a Kitchen Faucet
A 60–90 minute swap done properly: shutoffs, the basin wrench problem, supply lines and leak testing.
ReadRelated articles
How to Calculate Cement Bags for 1,000 Sq Ft (Slab, Plaster and Masonry)
The volume-to-bag method worked through for a slab, wall plaster and block mortar — with the mix-ratio table and the mistakes that double your order.
Read ConcreteHow Many 80lb Bags of Concrete Do I Need for a 10x10 Slab?
The short answer is 56 bags for a 4-inch slab — here is the simple math, the waste allowance, and when bagged mix stops making sense.
Read ConcreteConcrete vs Pavers: Which Is Better for Your Driveway?
Cost, durability, maintenance and curb appeal for the two most common driveway materials.
Read